The rollout of an application software upgrade has been planned. However, a back-out plan has not been developed. Which process or function should have provided the back-out plan?
The correct answer is C. Release management. You've hit your weekly limit · resets 5am (America/New_York)
Implementation and transition of new or changed services
Question
The rollout of an application software upgrade has been planned. However, a back-out plan has not been developed. Which process or function should have provided the back-out plan?
Options
- AAvailability management
- BChange management
- CRelease management
- DService desk
How the community answered
(26 responses)- A4% (1)
- B19% (5)
- C69% (18)
- D8% (2)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#release management#back-out plan#rollout#risk management