When can the building and testing of a Change begin?
The correct answer is C. As soon as the Request for Change (RFC) has been formally authorized. You've hit your weekly limit · resets 5am (America/New_York)
Control processes
Question
When can the building and testing of a Change begin?
Options
- AAs soon as the impact analysis has been discussed by the members of the Change Advisory
- BAs soon as there is a correct network plan for the change
- CAs soon as the Request for Change (RFC) has been formally authorized
- DAs soon as the Request for Change (RFC) has been classified
How the community answered
(35 responses)- A6% (2)
- B9% (3)
- C83% (29)
- D3% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#change management#RFC authorization#change lifecycle#change building