ITSM20F.EN · Question #119

Which Changes should be documented through formal change records?

The correct answer is A. infrastructure changes. You've hit your weekly limit · resets 5am (America/New_York)

Control processes

Question

Which Changes should be documented through formal change records?

Options

  • Ainfrastructure changes
  • Bchange in business strategy
  • Cstaff recruitment
  • Duser training

How the community answered

(38 responses)
  • A
    74% (28)
  • B
    16% (6)
  • C
    5% (2)
  • D
    5% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#change management#formal change records#infrastructure changes#change scope