Which of these would fall outside the scope of a typical service change management process?

The correct answer is D. A change to a business process that depends on IT Services. See the full explanation below for the reasoning.

Question

Which of these would fall outside the scope of a typical service change management process?

Options

  • AA change to a contract with a supplier
  • BA firmware upgrade to a server that is only used for IT Service Continuity purposes
  • CAn urgent need to replace a CPU to restore a service during an incident
  • DA change to a business process that depends on IT Services

How the community answered

(18 responses)
  • A
    17% (3)
  • B
    6% (1)
  • C
    6% (1)
  • D
    72% (13)