nerdexam
PeopleCert

ITIL · Question #297

Which of the following would be carried out as part of a post-project benefits review?

The correct answer is B. A review of the performance of the project's products in operational use and identification of. A PRINCE2 post-project benefits review assesses whether the project's products have delivered the expected benefits once in operational use.

The ITIL service lifecycle

Question

Which of the following would be carried out as part of a post-project benefits review?

Options

  • AAn assessment of whether the project fulfilled its original objectives
  • BA review of the performance of the project's products in operational use and identification of
  • CAn assessment of the project's risk management procedure
  • DA review of the performance of the project management method and the project management

How the community answered

(13 responses)
  • A
    8% (1)
  • B
    92% (12)

Why each option

A PRINCE2 post-project benefits review assesses whether the project's products have delivered the expected benefits once in operational use.

AAn assessment of whether the project fulfilled its original objectives

Assessing whether the project fulfilled its original objectives is part of the End Project Report produced during project closure, not the post-project benefits review.

BA review of the performance of the project's products in operational use and identification ofCorrect

In PRINCE2, a post-project benefits review is conducted after the project has closed and the products are being used operationally. Its primary purpose is to measure whether the expected benefits from the Business Case have been realised, and to identify any residual benefits still to come or any unintended outcomes - making actual operational performance the central focus.

CAn assessment of the project's risk management procedure

A review of the project's risk management procedure is part of lessons learned and the End Project Report, not the post-project benefits review.

DA review of the performance of the project management method and the project management

Reviewing the performance of the project management method and team is captured in lessons learned documentation during project closure, not in the post-project benefits review.

Concept tested: PRINCE2 post-project benefits review purpose

Source: https://www.axelos.com/certifications/prince2/prince2-7-foundation

Topics

#post-project review#benefits review#service transition#operational performance

Community Discussion

No community discussion yet for this question.

Full ITIL Practice