ITIL · Question #172

ITIL Question #172: Real Exam Question with Answer & Explanation

The correct answer is D: Future business requirements for IT services are quantified, designed, planned and implemented in a. See the full explanation below for the reasoning.

Question

What is the primary focus of business capacity management?

Options

  • AManagement, control and prediction of the performance, utilization and capacity of individual elements
  • BReview of all capacity supplier agreements and underpinning contracts with supplier management
  • CManagement, control and prediction of the end-to-end performance and capacity of the live, operational
  • DFuture business requirements for IT services are quantified, designed, planned and implemented in a