ITIL-FOUNDATION · Question #233
Which of the following statements correctly states the relationship between urgency, priority and impact?
The correct answer is D. Priority should be based on impact and urgency. In ITIL Incident and Problem Management, priority is always derived from a combination of impact and urgency, not the other way around.
Question
Which of the following statements correctly states the relationship between urgency, priority and impact?
Options
- AImpact, priority and urgency are independent of each other
- BUrgency should be based on impact and priority
- CImpact should be based on urgency and priority
- DPriority should be based on impact and urgency
How the community answered
(50 responses)- A4% (2)
- B2% (1)
- C8% (4)
- D86% (43)
Why each option
In ITIL Incident and Problem Management, priority is always derived from a combination of impact and urgency, not the other way around.
Impact and urgency are not independent of priority - they are the direct inputs used to calculate priority according to ITIL's priority matrix model.
Urgency is an independent assessment of time-sensitivity required by the business and is not derived from impact or priority - it is one of the inputs to priority.
Impact is an independent measure of business effect and is not derived from urgency or priority - it is the other primary input into the priority calculation.
Priority is determined by assessing two independent inputs - impact (the degree of effect on business processes or users) and urgency (how quickly the business needs a resolution). A priority matrix combining these two factors produces the final priority score, ensuring that resources are allocated to the most business-critical items first.
Concept tested: ITIL priority calculation from impact and urgency
Source: https://wiki.en.it-processmaps.com/index.php/Incident_Management#Incident_Prioritization