Targets for resolution should be based on priority. When scheduling Incident or Problem resolution, which of the following should not be taken into account?
The correct answer is D. Correct. This is not relevant when scheduling resolution. It is relevant when identifying. See the full explanation below for the reasoning.
Question
Targets for resolution should be based on priority. When scheduling Incident or Problem resolution, which of the following should not be taken into account?
Options
- AIncorrect. This is a relevant aspect for scheduling Incident or Problem resolution.
- BIncorrect. This is a relevant aspect for scheduling Incident or Problem resolution.
- CIncorrect. This is a relevant aspect for scheduling Incident or Problem resolution.
- DCorrect. This is not relevant when scheduling resolution. It is relevant when identifying
How the community answered
(22 responses)- A9% (2)
- B5% (1)
- C5% (1)
- D82% (18)