What is the correct way to make a change to a contract as a result of a major review of an authorized contract?

The correct answer is B. Correct. Any changes to the contract shall be subject to the Change Management process. service review meetings to discuss changes to the service scope, SLA, contract etc. Changes to the contract(s) resulting from these meetings will be subject to the Change Management process. Relationship Management process). of the contract. Any changes to the contract shall be…

Control Processes

Question

What is the correct way to make a change to a contract as a result of a major review of an authorized contract?

Options

  • AIncorrect. The Business Relationship Management process is responsible for setting up
  • BCorrect. Any changes to the contract shall be subject to the Change Management process.
  • CIncorrect. These representatives will be involved via other processes (e.g. Business
  • DIncorrect. Supplier Management is responsible for having a process in place for a major review

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    76% (35)
  • C
    13% (6)
  • D
    9% (4)

Explanation

service review meetings to discuss changes to the service scope, SLA, contract etc. Changes to the contract(s) resulting from these meetings will be subject to the Change Management process. Relationship Management process). of the contract. Any changes to the contract shall be subject to the Change Management process.

Topics

#contract management#Change Management#supplier contracts#Business Relationship Management