ISO20KF · Question #44

What is the recommendation with regard to the implementation of an emergency Change?

The correct answer is D. Correct. It is recommended that the Change process should be followed where possible. recommendation about who does this. bypassed and covered later. recommendation for a separate process. although any activities bypassed should be undertaken as soon as possible.

Control Processes

Question

What is the recommendation with regard to the implementation of an emergency Change?

Options

  • AIncorrect. The authorization of the emergency Change is part of the process and there is no
  • BIncorrect. It is not recommended to bypass the whole process although some activities may be
  • CIncorrect. There is a requirement for a separate policy for emergency Changes but not a
  • DCorrect. It is recommended that the Change process should be followed where possible

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    13% (5)
  • D
    77% (30)

Explanation

recommendation about who does this. bypassed and covered later. recommendation for a separate process. although any activities bypassed should be undertaken as soon as possible.

Topics

#emergency change#Change Management#change authorization#change process