In which of the following contract types does the buyer have the most cost risk?
The correct answer is A. Cost plus percentage of costs (CPPC). You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
In which of the following contract types does the buyer have the most cost risk?
Options
- ACost plus percentage of costs (CPPC)
- BCost plus fixed fee (CPFF)
- CCost plus award fee (CPAF)
- DCost plus incentive fee (CPIF)
How the community answered
(35 responses)- A83% (29)
- B3% (1)
- C11% (4)
- D3% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#contract types#CPPC#buyer cost risk#cost reimbursable contracts