ISEB-PM1 · Question #83
The widget production project is well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of…
The correct answer is A. Control limits. You've hit your session limit · resets 10:20pm (America/New_York)
Quality Management
Question
The widget production project is well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgets inspected, 47 percent fell within the acceptable weight range. This is an example of:
Options
- AControl limits.
- BQuality assurance.
- CControl charting.
- DCorrective action.
How the community answered
(43 responses)- A72% (31)
- B7% (3)
- C16% (7)
- D5% (2)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#control limits#quality control#statistical sampling#acceptance criteria