nerdexam
BCS-ISEB

ISEB-PM1 · Question #78

ISEB-PM1 Question #78: Real Exam Question with Answer & Explanation

Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #78. The question stem and answer options stay visible for context.

Question

The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:

Options

  • AThe team is making sure the seller does not cut scope.
  • BAll costs invoiced are being audited.
  • CThere can only be a maximum 10 percent increase if there is an unexpected cost overrun.
  • DThe fee is only received by the seller when the project is completed.

Unlock ISEB-PM1 to see the answer

You've previewed enough free ISEB-PM1 questions. Unlock ISEB-PM1 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full ISEB-PM1 Practice