Which of the following is the LEAST effective way to influence the factors that create changes to the cost baseline?
The correct answer is D. Notify all stakeholders that no more changes will be allowed. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
Which of the following is the LEAST effective way to influence the factors that create changes to the cost baseline?
Options
- AReview the project scope with the functional manager responsible for the greatest number of
- BExplain to those requesting changes the negative impact of change to the project.
- CEliminate the scope causing the most changes.
- DNotify all stakeholders that no more changes will be allowed.
How the community answered
(29 responses)- A7% (2)
- B3% (1)
- C17% (5)
- D72% (21)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#cost baseline#change management#scope control#stakeholder management