Project A has a NPV of $275K US over 2.5 years. Project B has an IRR of 3.2%. Project C has a BCR of 0.89:1. Project D has four people on it and is encountering scope creep. Which of the following…

The correct answer is C. Project C. Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially CiscoVendor: ISEB Exam Name: Foundation Certificate in Project Management , Juniper, Check Point, LPI, Nortel, EXIN and so on…

Project Planning

Question

Project A has a NPV of $275K US over 2.5 years. Project B has an IRR of 3.2%. Project C has a BCR of 0.89:1. Project D has four people on it and is encountering scope creep. Which of the following projects would stand the greatest chance of getting cancelled?

Options

  • AProject A
  • BProject B
  • CProject C
  • DProject D

How the community answered

(64 responses)
  • A
    13% (8)
  • B
    6% (4)
  • C
    78% (50)
  • D
    3% (2)

Explanation

Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially CiscoVendor: ISEB Exam Name: Foundation Certificate in Project Management , Juniper, Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#benefit cost ratio#project selection#NPV#IRR