The IT initiative project is on schedule and under budget. The customer is pleased, but would like a scope change. As a result, a new team is brought in to help the existing team implement this…

The correct answer is A. Milestone chart. You've hit your weekly limit · resets 5am (America/New_York)

Communication Management

Question

The IT initiative project is on schedule and under budget. The customer is pleased, but would like a scope change. As a result, a new team is brought in to help the existing team implement this scope change. Before the team arrives, senior management would like to see where the project stands. Which of the following do you show them?

Options

  • AMilestone chart
  • BGantt chart
  • CWork breakdown structure
  • DNetwork diagram

How the community answered

(43 responses)
  • A
    77% (33)
  • B
    12% (5)
  • C
    7% (3)
  • D
    5% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#milestone chart#status reporting#project communication#senior management reporting