nerdexam
BCS-ISEB

ISEB-PM1 · Question #543

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

The correct answer is C. 6. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

Options

  • A6.1
  • B6.3
  • C6
  • D4

How the community answered

(64 responses)
  • A
    3% (2)
  • B
    14% (9)
  • C
    77% (49)
  • D
    6% (4)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#PERT#weighted average#duration estimation#schedule

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice