Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
The correct answer is C. 6. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
Options
- A6.1
- B6.3
- C6
- D4
How the community answered
(64 responses)- A3% (2)
- B14% (9)
- C77% (49)
- D6% (4)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#PERT#weighted average#duration estimation#schedule