Giving a part of project work to a contractor is an example of:

The correct answer is D. risk deflection. You've hit your weekly limit · resets 5am (America/New_York)

Risk Management

Question

Giving a part of project work to a contractor is an example of:

Options

  • Arisk assumption
  • Brisk assignment
  • Crisk delegation
  • Drisk deflection
  • Erisk mitigation

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    10% (3)
  • D
    83% (25)
  • E
    3% (1)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#risk deflection#risk transfer#contractor#outsourcing