Question

Which of the following is not true for a Responsibility Assignment Matrix (RAM):

Options

  • ADefines what project member is responsible for each activity
  • BDefines all people associated with each activity
  • CDefines responsibilities for each WBS component
  • DAll of the other alternatives apply