The resource calendars document is an output of which process?

The correct answer is B. Acquire Project Team. You've hit your weekly limit · resets 5am (America/New_York)

Resource Management

Question

The resource calendars document is an output of which process?

Options

  • AEstimate Activity Resources
  • BAcquire Project Team
  • CDevelop Schedule
  • DDevelop Project Team

How the community answered

(30 responses)
  • A
    17% (5)
  • B
    70% (21)
  • C
    3% (1)
  • D
    10% (3)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#resource calendars#acquire project team#process outputs#resource management