The resource calendars document is an output of which process?
The correct answer is B. Acquire Project Team. You've hit your weekly limit · resets 5am (America/New_York)
Resource Management
Question
The resource calendars document is an output of which process?
Options
- AEstimate Activity Resources
- BAcquire Project Team
- CDevelop Schedule
- DDevelop Project Team
How the community answered
(30 responses)- A17% (5)
- B70% (21)
- C3% (1)
- D10% (3)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#resource calendars#acquire project team#process outputs#resource management