ISEB-PM1 · Question #430
Which of the following is a tool and technique to develop the schedule?
The correct answer is A. What-if scenario analysis. What-if scenario analysis is a recognized tool and technique in the PMBOK's Develop Schedule process. It involves evaluating different scenarios (e.g., "What if a resource is unavailable for two weeks?") to assess their effect on the project timeline and find the best path…
Question
Which of the following is a tool and technique to develop the schedule?
Options
- AWhat-if scenario analysis
- BBenchmarking
- CVariance analysis
- DSWOT analysis
How the community answered
(37 responses)- A84% (31)
- B5% (2)
- C3% (1)
- D8% (3)
Explanation
What-if scenario analysis is a recognized tool and technique in the PMBOK's Develop Schedule process. It involves evaluating different scenarios (e.g., "What if a resource is unavailable for two weeks?") to assess their effect on the project timeline and find the best path forward - making it directly applicable to schedule creation.
Why the distractors are wrong:
- B. Benchmarking is used in Plan Quality Management, not schedule development - it compares your project practices against other projects or industry standards.
- C. Variance analysis is used in Control Schedule (monitoring and controlling), where you compare planned vs. actual performance after execution has begun - not during schedule creation.
- D. SWOT analysis (Strengths, Weaknesses, Opportunities, Threats) belongs to risk management and strategic planning, not schedule development.
Memory tip: Group the answers by process group. What-if scenario analysis is a planning tool - you ask "what if?" before things go wrong to stress-test your schedule. Variance analysis is reactive (controlling), and SWOT/benchmarking live in other knowledge areas entirely. When you see "develop schedule," think forward-looking analytical tools like what-if, schedule compression, and resource optimization.