Which of the following is one of the tools and techniques for the Define Activities process?
The correct answer is A. Rolling wave planning. Rolling wave planning belongs to Define Activities because it directly governs how activities are identified - near-term work is planned in detail while future work remains at a higher level until more information is available. It's a technique that shapes the activity…
Question
Which of the following is one of the tools and techniques for the Define Activities process?
Options
- ARolling wave planning
- BDependency determination
- CSchedule network template
- DApplying leads and lags
How the community answered
(38 responses)- A71% (27)
- B16% (6)
- C8% (3)
- D5% (2)
Explanation
Rolling wave planning belongs to Define Activities because it directly governs how activities are identified - near-term work is planned in detail while future work remains at a higher level until more information is available. It's a technique that shapes the activity definition process itself, making it a natural fit here.
Why the distractors are wrong:
- B. Dependency determination belongs to Sequence Activities, where you establish relationships (mandatory, discretionary, external/internal) between already-defined activities.
- C. Schedule network template is an organizational process asset used in Sequence Activities to speed up network diagram creation - it doesn't help define what activities exist.
- D. Applying leads and lags also belongs to Sequence Activities, used to refine the timing relationships between activities once sequencing is underway.
Memory tip: Think of Define Activities as "what do we do?" and Sequence Activities as "in what order?" - Dependency determination, network templates, and leads/lags are all about order, so they belong to Sequence. Rolling wave planning is about how thoroughly you define activities now vs. later, so it stays in Define.