Which of the following tools or techniques is used for Estimate Activity Duration?

The correct answer is D. Parametric. Parametric estimating uses statistical relationships between historical data and project variables (e.g., hours per unit, cost per square foot) to mathematically calculate activity durations, making it a direct tool for the Estimate Activity Duration process in PMBOK. Why the…

Project Planning

Question

Which of the following tools or techniques is used for Estimate Activity Duration?

Options

  • ACritical path
  • BRolling Wave
  • CPDM
  • DParametric

How the community answered

(63 responses)
  • A
    13% (8)
  • B
    3% (2)
  • C
    8% (5)
  • D
    76% (48)

Explanation

Parametric estimating uses statistical relationships between historical data and project variables (e.g., hours per unit, cost per square foot) to mathematically calculate activity durations, making it a direct tool for the Estimate Activity Duration process in PMBOK.

Why the distractors are wrong:

  • A. Critical Path belongs to the Develop Schedule process - it identifies the longest sequence of activities but says nothing about how long individual activities take.
  • B. Rolling Wave Planning is a progressive elaboration technique used in Define Activities, where near-term work is planned in detail while future work stays at a high level.
  • C. PDM (Precedence Diagramming Method) is used in Sequence Activities to map logical relationships (FS, SS, FF, SF) between activities - it's about order, not duration.

Memory tip: Think "Parameters measure duration" - Parametric = plugging known rates or quantities into a formula to measure how long something takes. The other three tools deal with scheduling, sequencing, or defining work - all after you've already estimated.

Topics

#activity duration estimating#parametric estimating#duration estimation#techniques