ISEB-PM1 · Question #245
Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
The correct answer is D. Reserve Analysis. Reserve Analysis is correct because it is the technique specifically designed to add contingency reserves (buffer time) to activity duration estimates to account for schedule uncertainty and risk - its entire purpose is to build in extra time "just in case." Analogous…
Question
Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
Options
- AAnalogous Estimating
- BExpert Judgment
- COptimistic Estimates
- DReserve Analysis
How the community answered
(44 responses)- A7% (3)
- B7% (3)
- C2% (1)
- D84% (37)
Explanation
Reserve Analysis is correct because it is the technique specifically designed to add contingency reserves (buffer time) to activity duration estimates to account for schedule uncertainty and risk - its entire purpose is to build in extra time "just in case."
Analogous Estimating (A) uses historical data from similar past projects to estimate duration; it approximates based on precedent but does not inherently add contingency buffers. Expert Judgment (B) leverages the knowledge of experienced individuals to inform estimates, but is a general input technique rather than one focused on contingency. Optimistic Estimates (C) - a term associated with PERT analysis - represents the best-case scenario and actually minimizes estimated time rather than adding buffer.
Memory tip: Think of "reserve" like a financial reserve fund - you set it aside specifically for unexpected costs (or in this case, unexpected delays). If the question mentions contingency, padding, or buffer time, the answer almost always involves Reserve Analysis.