The correct answer is B. Resource Leveling. See the full explanation below for the reasoning.

Question

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options

  • AApplying calendars
  • BResource Leveling
  • CResource Planning
  • DResource Conflict Management