nerdexam
BCS-ISEB

ISEB-PM1 · Question #246

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

The correct answer is B. Resource Leveling. Resource Leveling is applied after a Critical Path Method (CPM) calculation when resource availability is constrained - it adjusts start and finish dates to balance resource demand against supply, often extending the project schedule to avoid over-allocation. Why the…

Resource Management

Question

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options

  • AApplying calendars
  • BResource Leveling
  • CResource Planning
  • DResource Conflict Management

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    76% (26)
  • C
    3% (1)
  • D
    9% (3)

Explanation

Resource Leveling is applied after a Critical Path Method (CPM) calculation when resource availability is constrained - it adjusts start and finish dates to balance resource demand against supply, often extending the project schedule to avoid over-allocation.

Why the distractors are wrong:

  • A. Applying calendars - Calendars define working/non-working time and are inputs to the schedule model, not a post-CPM optimization technique for resource constraints.
  • C. Resource Planning - This is a broader planning process (identifying what resources are needed), not a network analysis technique applied after CPM.
  • D. Resource Conflict Management - Not a defined PMI schedule network analysis technique; it's a general concept, not a named method in the PMBOK framework.

Memory tip: Think of Resource Leveling as "smoothing the hill" - after CPM identifies your critical path, leveling flattens resource peaks and valleys so no resource is overloaded, even if it means pushing the schedule out. CPM first, then Level - the sequence is your cue.

Topics

#resource leveling#schedule network analysis#resource availability#critical path

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice