ISEB-PM1 · Question #246
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
The correct answer is B. Resource Leveling. Resource Leveling is applied after a Critical Path Method (CPM) calculation when resource availability is constrained - it adjusts start and finish dates to balance resource demand against supply, often extending the project schedule to avoid over-allocation. Why the…
Question
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Options
- AApplying calendars
- BResource Leveling
- CResource Planning
- DResource Conflict Management
How the community answered
(34 responses)- A12% (4)
- B76% (26)
- C3% (1)
- D9% (3)
Explanation
Resource Leveling is applied after a Critical Path Method (CPM) calculation when resource availability is constrained - it adjusts start and finish dates to balance resource demand against supply, often extending the project schedule to avoid over-allocation.
Why the distractors are wrong:
- A. Applying calendars - Calendars define working/non-working time and are inputs to the schedule model, not a post-CPM optimization technique for resource constraints.
- C. Resource Planning - This is a broader planning process (identifying what resources are needed), not a network analysis technique applied after CPM.
- D. Resource Conflict Management - Not a defined PMI schedule network analysis technique; it's a general concept, not a named method in the PMBOK framework.
Memory tip: Think of Resource Leveling as "smoothing the hill" - after CPM identifies your critical path, leveling flattens resource peaks and valleys so no resource is overloaded, even if it means pushing the schedule out. CPM first, then Level - the sequence is your cue.