The correct answer is C. Performance measurements. See the full explanation below for the reasoning.

Question

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

Options

  • APerformance organizations
  • BSchedule baselines
  • CPerformance measurements
  • DChange requests