ISEB-PM1 · Question #235

An input required to develop a preliminary project scope statement is: ISEB ISEB-PM1 Exam

The correct answer is B. Organizational Process Assets. Organizational Process Assets (B) are correct because they include existing organizational plans, policies, procedures, templates, and historical information that directly feed into developing a preliminary project scope statement - they give you the organizational context and…

Project Planning

Question

An input required to develop a preliminary project scope statement is:

ISEB ISEB-PM1 Exam

Options

  • AOrganizational Structure
  • BOrganizational Process Assets
  • COrganizational Matrix
  • DOrganizational Breakdown Structures

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    74% (34)
  • C
    7% (3)
  • D
    15% (7)

Explanation

Organizational Process Assets (B) are correct because they include existing organizational plans, policies, procedures, templates, and historical information that directly feed into developing a preliminary project scope statement - they give you the organizational context and reusable artifacts needed to define scope early.

Why the distractors are wrong:

  • A (Organizational Structure) describes how the organization is arranged (functional, projectized, matrix) - it influences authority and reporting, not scope definition inputs.
  • C (Organizational Matrix) is not a standard PMBOK input term; it conflates "matrix organization" (a structure type) with process inputs - a distractor playing on familiar terminology.
  • D (Organizational Breakdown Structure) is an output/tool used to map project work to organizational units; it's produced during planning, not used as an input to define preliminary scope.

Memory tip: Think of "assets" as your organizational toolkit - templates, lessons learned, and historical records are assets you bring into a project. Whenever a question asks what you need to start something, look for process assets, because they're the organization's inherited knowledge that enables planning.

Topics

#scope statement#organizational process assets#process inputs#initiation

Community Discussion

No community discussion yet for this question.