ISEB-PM1 · Question #234
Which tool or technique measures performance of the project as it moves from project initiation through project closure?
The correct answer is D. Earned value. Earned Value (D) integrates scope, schedule, and cost data to measure project performance at any point during the project lifecycle - from initiation through closure - giving a quantitative snapshot of how much work is done versus how much was planned and what it cost. Why the…
Question
Which tool or technique measures performance of the project as it moves from project initiation through project closure?
Options
- AResource leveling
- BParametric measuring
- CPareto chart
- DEarned value
How the community answered
(70 responses)- A3% (2)
- B10% (7)
- C4% (3)
- D83% (58)
Explanation
Earned Value (D) integrates scope, schedule, and cost data to measure project performance at any point during the project lifecycle - from initiation through closure - giving a quantitative snapshot of how much work is done versus how much was planned and what it cost.
Why the distractors are wrong:
- Resource leveling (A) is a scheduling technique that adjusts resource assignments to resolve over-allocation; it manages resources, not performance measurement.
- Parametric measuring (B) is not a standard PMI term; parametric estimating uses statistical relationships to estimate costs or durations, but it's an estimating technique, not a performance tracking tool.
- Pareto chart (C) is a quality management tool that ranks defects or problems by frequency; it analyzes causes of issues, not ongoing project performance against a baseline.
Memory tip: Think of EV as your project's "report card" - just as a report card tracks your progress from the first day of school to the last, Earned Value tracks project performance from start to finish using three key metrics: Planned Value (PV), Earned Value (EV), and Actual Cost (AC).