What is one of the MAJOR outputs of activity sequencing?
The correct answer is C. Project network diagram. Activity sequencing is the process of identifying and documenting relationships among project activities, and its primary output is the Project Network Diagram (C) - a visual representation showing the logical sequence and dependencies between activities (e.g., a Precedence…
Question
What is one of the MAJOR outputs of activity sequencing?
Options
- AResponsibility assignment matrix
- BWork breakdown structure update
- CProject network diagram
- DMandatory dependencies list
How the community answered
(29 responses)- A17% (5)
- B7% (2)
- C72% (21)
- D3% (1)
Explanation
Activity sequencing is the process of identifying and documenting relationships among project activities, and its primary output is the Project Network Diagram (C) - a visual representation showing the logical sequence and dependencies between activities (e.g., a Precedence Diagramming Method chart). This diagram is the core deliverable because it directly results from ordering activities and establishing their relationships.
Why the distractors are wrong:
- A (Responsibility Assignment Matrix): This maps team members to WBS components - it's an output of resource planning, not sequencing.
- B (Work Breakdown Structure update): The WBS is created during scope definition/decomposition, not sequencing. Sequencing assumes the WBS already exists.
- D (Mandatory dependencies list): This is an input to activity sequencing (it informs how activities must be ordered), not an output of it.
Memory tip: Think of sequencing as "drawing the roadmap." The network diagram is that roadmap - it's what you produce when you connect the dots between activities. If you remember "sequencing = network diagram," you'll always pick C.