Which control chart is used to monitor the number of defects when the opportunity count varies?
The correct answer is D. U-chart. U-chart (D) is correct because it monitors the number of defects per unit when the opportunity for defects varies across samples - for example, inspecting fabric bolts of different lengths or circuit boards with different component counts. By expressing defects as a rate per…
Question
Which control chart is used to monitor the number of defects when the opportunity count varies?
Options
- AC-chart
- BP-chart
- CNP-chart
- DU-chart
How the community answered
(54 responses)- A4% (2)
- B11% (6)
- C6% (3)
- D80% (43)
Explanation
U-chart (D) is correct because it monitors the number of defects per unit when the opportunity for defects varies across samples - for example, inspecting fabric bolts of different lengths or circuit boards with different component counts. By expressing defects as a rate per unit, the U-chart normalizes for varying sample sizes, making comparisons valid.
Why the distractors are wrong:
- C-chart (A) also tracks defect counts, but requires a constant opportunity size - use it when every sample has the same inspection area.
- P-chart (B) handles variable sample sizes, but monitors the proportion of defective items (pass/fail), not the count of defects within items.
- NP-chart (C) monitors the number of defective items, but requires a constant sample size.
Memory tip: Think of the four charts in a 2×2 grid - rows are "defects" vs "defectives," columns are "constant" vs "variable" sample size. U = defects + variable (U for "Unequal units"). If you can remember that U-chart is the defect-counting chart that handles unequal sample sizes, the others fall into place by elimination.