Which control chart is used to monitor the number of defects when the opportunity count varies?

The correct answer is D. U-chart. U-chart (D) is correct because it monitors the number of defects per unit when the opportunity for defects varies across samples - for example, inspecting fabric bolts of different lengths or circuit boards with different component counts. By expressing defects as a rate per…

Control

Question

Which control chart is used to monitor the number of defects when the opportunity count varies?

Options

  • AC-chart
  • BP-chart
  • CNP-chart
  • DU-chart

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    11% (6)
  • C
    6% (3)
  • D
    80% (43)

Explanation

U-chart (D) is correct because it monitors the number of defects per unit when the opportunity for defects varies across samples - for example, inspecting fabric bolts of different lengths or circuit boards with different component counts. By expressing defects as a rate per unit, the U-chart normalizes for varying sample sizes, making comparisons valid.

Why the distractors are wrong:

  • C-chart (A) also tracks defect counts, but requires a constant opportunity size - use it when every sample has the same inspection area.
  • P-chart (B) handles variable sample sizes, but monitors the proportion of defective items (pass/fail), not the count of defects within items.
  • NP-chart (C) monitors the number of defective items, but requires a constant sample size.

Memory tip: Think of the four charts in a 2×2 grid - rows are "defects" vs "defectives," columns are "constant" vs "variable" sample size. U = defects + variable (U for "Unequal units"). If you can remember that U-chart is the defect-counting chart that handles unequal sample sizes, the others fall into place by elimination.