An important factor in a viable Control Plan is to determine who, when and to what level various personnel must be _________ to maintain the improvements made to a process.

The correct answer is C. Trained. Training (C) is the correct answer because a Control Plan must define who needs to be trained, when training should occur, and the depth of training required - ensuring that employees can sustain process improvements after a project closes. Without a deliberate training…

Control

Question

An important factor in a viable Control Plan is to determine who, when and to what level various personnel must be _________ to maintain the improvements made to a process.

Options

  • ATransferred
  • BPromoted
  • CTrained
  • DDismissed

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    84% (21)
  • D
    8% (2)

Explanation

Training (C) is the correct answer because a Control Plan must define who needs to be trained, when training should occur, and the depth of training required - ensuring that employees can sustain process improvements after a project closes. Without a deliberate training strategy, gains erode as people revert to old habits or new employees lack the necessary knowledge.

  • A (Transferred) is wrong because moving personnel around doesn't inherently preserve process improvements; it can actually disrupt them if trained people leave a role.
  • B (Promoted) is wrong because advancement is an HR function unrelated to sustaining a Control Plan.
  • D (Dismissed) is wrong because removing personnel is the opposite of building the capability needed to maintain improvements.

Memory tip: Think of the three W's in a Control Plan - Who, When, and What level - all pointing to the word Train, because Training is how you Transfer knowledge into the process permanently.