An important factor in a viable Control Plan is to determine who, when and to what level various personnel must be _________ to maintain the improvements made to a process.
The correct answer is C. Trained. Training (C) is the correct answer because a Control Plan must define who needs to be trained, when training should occur, and the depth of training required - ensuring that employees can sustain process improvements after a project closes. Without a deliberate training…
Question
An important factor in a viable Control Plan is to determine who, when and to what level various personnel must be _________ to maintain the improvements made to a process.
Options
- ATransferred
- BPromoted
- CTrained
- DDismissed
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C84% (21)
- D8% (2)
Explanation
Training (C) is the correct answer because a Control Plan must define who needs to be trained, when training should occur, and the depth of training required - ensuring that employees can sustain process improvements after a project closes. Without a deliberate training strategy, gains erode as people revert to old habits or new employees lack the necessary knowledge.
- A (Transferred) is wrong because moving personnel around doesn't inherently preserve process improvements; it can actually disrupt them if trained people leave a role.
- B (Promoted) is wrong because advancement is an HR function unrelated to sustaining a Control Plan.
- D (Dismissed) is wrong because removing personnel is the opposite of building the capability needed to maintain improvements.
Memory tip: Think of the three W's in a Control Plan - Who, When, and What level - all pointing to the word Train, because Training is how you Transfer knowledge into the process permanently.