CCBA · Question #627

A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previo

The correct answer is D. Create requirement relationships. Creating requirement relationshipshelps the BAunderstand how a change in one requirement affects others, making impact analysis more effective. BABOK® Guide (Chapter 5.1 - Trace Requirements)states thatestablishing requirement relationships helps determine dependencies and assess

Requirements Life Cycle Management

Question

A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?

Options

  • APerform a risk analysis
  • BConduct a cost-benefit analysis
  • CCreate use case scenarios
  • DCreate requirement relationships

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    9% (2)
  • D
    73% (16)

Explanation

Creating requirement relationshipshelps the BAunderstand how a change in one requirement affects others, making impact analysis more effective. BABOK® Guide (Chapter 5.1 - Trace Requirements)states thatestablishing requirement relationships helps determine dependencies and assess the impact of changes. Risk analysis (Option A)assesses uncertainties but does not trace requirement dependencies. Cost-benefit analysis (Option B)evaluates financial feasibility but does not assess requirement Use case scenarios (Option C)define interactions but do not trace dependencies.

Topics

#impact analysis#requirement relationships#traceability#change management