A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previo
The correct answer is D. Create requirement relationships. Creating requirement relationshipshelps the BAunderstand how a change in one requirement affects others, making impact analysis more effective. BABOK® Guide (Chapter 5.1 - Trace Requirements)states thatestablishing requirement relationships helps determine dependencies and assess
Question
A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?
Options
- APerform a risk analysis
- BConduct a cost-benefit analysis
- CCreate use case scenarios
- DCreate requirement relationships
How the community answered
(22 responses)- A5% (1)
- B14% (3)
- C9% (2)
- D73% (16)
Explanation
Creating requirement relationshipshelps the BAunderstand how a change in one requirement affects others, making impact analysis more effective. BABOK® Guide (Chapter 5.1 - Trace Requirements)states thatestablishing requirement relationships helps determine dependencies and assess the impact of changes. Risk analysis (Option A)assesses uncertainties but does not trace requirement dependencies. Cost-benefit analysis (Option B)evaluates financial feasibility but does not assess requirement Use case scenarios (Option C)define interactions but do not trace dependencies.