CCBA · Question #194
You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are…
The correct answer is B. Requirements coverage. Requirements coverage is not one of the three reasons why trace requirements are useful. Requirements coverage is a measure of how well the requirements address the needs and objectives of the stakeholders and the project. Trace requirements are useful for the following…
Question
You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope. There are actually three reasons why the business analyst should trace requirements. Which one of the following is not one of the three reasons why trace requirements are useful?
Options
- ARequirements allocation
- BRequirements coverage
- CQuality control
- DImpact analysis
How the community answered
(18 responses)- A11% (2)
- B78% (14)
- C6% (1)
- D6% (1)
Explanation
Requirements coverage is not one of the three reasons why trace requirements are useful. Requirements coverage is a measure of how well the requirements address the needs and objectives of the stakeholders and the project. Trace requirements are useful for the following Requirements allocation: This is the process of assigning requirements to the components or deliverables that will satisfy them. Trace requirements help to ensure that each requirement is allocated to the appropriate component or deliverable, and that no requirement is left unallocated or over-allocated. Quality control: This is the process of verifying that the requirements and the deliverables meet the quality standards and criteria. Trace requirements help to ensure that the quality of the requirements and the deliverables can be assessed and validated, and that any defects or issues can be identified and resolved. Impact analysis: This is the process of assessing the potential effects of a change request or a problem on the requirements and the deliverables. Trace requirements help to determine the scope and magnitude of the impact, and the actions needed to address the change or the