You are hired as a contract project manager for Dreams Unlimited Inc. The project involves setting up ten servers and fifty client computers on the network. From past experience, you know it takes aro
The correct answer is C. Parametric modeling. Parametric modeling is an estimation technique that uses historical data and mathematical formulas to calculate estimates based on the relationship between variables. In this case, the variables are the number of servers and clients, and the hours required to install them. By mul
Question
You are hired as a contract project manager for Dreams Unlimited Inc. The project involves setting up ten servers and fifty client computers on the network. From past experience, you know it takes around fifteen hours to install, test, and finalize a server, while it takes only ten hours for a client. You consider these data for making an estimate of schedule of the task. Which of the following estimation techniques has been used?
Options
- ABottom-up
- BSchedule performance index
- CParametric modeling
- DAnalogous
How the community answered
(44 responses)- A2% (1)
- B7% (3)
- C80% (35)
- D11% (5)
Explanation
Parametric modeling is an estimation technique that uses historical data and mathematical formulas to calculate estimates based on the relationship between variables. In this case, the variables are the number of servers and clients, and the hours required to install them. By multiplying the number of servers by 15 hours, and the number of clients by 10 hours, you can get an estimate of the total hours needed for the project. This technique is useful when the project has a high level of similarity to past projects, and the data is reliable and scalable.