If a requirement has been satisfied, why is it still considered a requirement?
The correct answer is B. Requirements are considered requirements even if the requirements have been satisfied. According to the BABOK® Guide, a requirement is a usable representation of a need. A requirement does not cease to be a requirement once it has been satisfied; it remains a requirement as long as the need exists and the solution is in use. Requirements may change over time due…
Question
If a requirement has been satisfied, why is it still considered a requirement?
Options
- AA requirement is considered a requirement as long as the requirement may be able to be
- BRequirements are considered requirements even if the requirements have been satisfied.
- CA requirement is considered valid as long as the business stakeholders need it.
- DIf a requirement has been satisfied, it is no longer a requirement and should be purged from
How the community answered
(44 responses)- B91% (40)
- C7% (3)
- D2% (1)
Explanation
According to the BABOK® Guide, a requirement is a usable representation of a need. A requirement does not cease to be a requirement once it has been satisfied; it remains a requirement as long as the need exists and the solution is in use. Requirements may change over time due to changes in the business environment, stakeholder needs, or solution performance1.