CCBA · Question #122
You need to identify assumptions as part of the assessment of capability gaps. Which of the following is an example of an assumption?
The correct answer is A. The project manager believes that her project team members can program in COBOL.. According to the BABOK® Guide, an assumption is a factor that is considered to be true for the purposes of planning and analysis, but has not been confirmed or proven. Assumptions are used to fill in the gaps of knowledge or uncertainty, and may affect the outcome of the project
Question
You need to identify assumptions as part of the assessment of capability gaps. Which of the following is an example of an assumption?
Options
- AThe project manager believes that her project team members can program in COBOL.
- BThe software must be compatible with the current operating system.
- CThe risk in the project must be quantified.
- DAll vendors must have security clearance.
How the community answered
(19 responses)- A95% (18)
- C5% (1)
Explanation
According to the BABOK® Guide, an assumption is a factor that is considered to be true for the purposes of planning and analysis, but has not been confirmed or proven. Assumptions are used to fill in the gaps of knowledge or uncertainty, and may affect the outcome of the project if they turn out to be false. An example of an assumption is the project manager's belief that her project team members can program in COBOL, which may or may not be true, and may impact the project's feasibility, scope, cost, and schedule1.
Topics
Community Discussion