You are the business analyst for a smaller project where there are few requirements. Management would still like you to create a method to trace the few requirements for this project. What type of mat

The correct answer is B. Requirements trace matrix. According to the BABOK® Guide, a requirements trace matrix is a table that links requirements to their origin and traces them throughout the project life cycle. A requirements trace matrix is useful for tracking the status, priority, and satisfaction of requirements, as well as i

Requirements Life Cycle Management

Question

You are the business analyst for a smaller project where there are few requirements. Management would still like you to create a method to trace the few requirements for this project. What type of matrix would be best in this instance?

Options

  • ACoverage matrix
  • BRequirements trace matrix
  • CRoles and responsibility matrix
  • DRACI matrix

How the community answered

(58 responses)
  • A
    3% (2)
  • B
    90% (52)
  • C
    5% (3)
  • D
    2% (1)

Explanation

According to the BABOK® Guide, a requirements trace matrix is a table that links requirements to their origin and traces them throughout the project life cycle. A requirements trace matrix is useful for tracking the status, priority, and satisfaction of requirements, as well as identifying dependencies, gaps, and overlaps. A requirements trace matrix is suitable for smaller projects where there are few requirements, as it can provide a simple and effective way to trace the few requirements for the project1.

Topics

#traceability matrix#requirements tracing#coverage matrix

Community Discussion

No community discussion yet for this question.