CCBA · Question #427

A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not…

The correct answer is B. Consult with the business owner to discuss possible trade-oils. The project team should consult with the business owner to discuss possible trade-offs when prioritizing requirements. Trade-offs are compromises or concessions that are made to balance conflicting or competing factors or criteria. Trade-offs can help to resolve disagreements…

Requirements Life Cycle Management

Question

A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?

Options

  • AChange the priority of the requirements by performing are ranking
  • BConsult with the business owner to discuss possible trade-oils
  • CImplement the requirements that the project team considers important
  • DExecute the requirements that the business owner identified

How the community answered

(55 responses)
  • A
    9% (5)
  • B
    84% (46)
  • C
    5% (3)
  • D
    2% (1)

Explanation

The project team should consult with the business owner to discuss possible trade-offs when prioritizing requirements. Trade-offs are compromises or concessions that are made to balance conflicting or competing factors or criteria. Trade-offs can help to resolve disagreements or disputes among stakeholders regarding the relative importance or urgency of requirements. Requirements are conditions or capabilities that a stakeholder needs or wants from a solution. The other options are incorrect because: Option A is incorrect because changing the priority of the requirements by performing a ranking is not a collaborative technique, but an analytical technique. Ranking is a method of assigning scores or values to requirements based on predefined criteria or scales. Ranking can help to compare and order requirements according to their significance or relevance for a solution, but it does not involve stakeholder input or feedback. Option C is incorrect because implementing the requirements that the project team considers important is not a collaborative technique, but an authoritative technique. Authoritative techniques are based on the power or influence of a single person or group over others. Authoritative techniques can help to expedite or simplify the decision-making process, but they may not reflect the consensus or agreement of all stakeholders. Option D is incorrect because executing the requirements that the business owner identified is not a collaborative technique, but an authoritative technique. Authoritative techniques are based on the power or influence of a single person or group over others. Authoritative techniques can help to expedite or simplify the decision-making process, but they may not reflect the consensus or agreement of all stakeholders.

Topics

#requirements prioritization#stakeholder negotiation#trade-offs#conflict resolution