CCBA · Question #626
A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to
The correct answer is A. Use a rigorous approval process of detailed specifications.. Given significant regulatory risks, arigorous approval processis required to ensure thatall legal, compliance, and stakeholder requirements are met before implementation. BABOK® Guide (Chapter 4.4 - Approve Requirements)states thathigh-risk projects, such as regulatory implementa
Question
A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. According to the BABOK® Guide, what will the BA need to do?
Options
- AUse a rigorous approval process of detailed specifications.
- BEnsure the document is completed and signed off.
- CUse an informal approval process to speed up delivery.
- DEnsure high-level user stories are completed and accepted.
How the community answered
(54 responses)- A78% (42)
- B13% (7)
- C6% (3)
- D4% (2)
Explanation
Given significant regulatory risks, arigorous approval processis required to ensure thatall legal, compliance, and stakeholder requirements are met before implementation. BABOK® Guide (Chapter 4.4 - Approve Requirements)states thathigh-risk projects, such as regulatory implementations, require formal validation and approval processes to avoid compliance failures. Simply completing and signing off documents (Option B)does not ensure a proper validation Informal approval (Option C)is inappropriate for high-risk projects. High-level user stories (Option D)are insufficient for compliance-based projects.