CCBA · Question #580
A business analyst (BA) is developing requirements for a project with a limited budget. The business owner will be prioritizing requirements so that low-value requirements can be de-scoped and the…
The correct answer is A. Dependencies. Dependencies between requirements impact prioritization decisions, as some requirements may be critical to enabling others. If dependent requirements are removed, they mayaffect overall system functionality. BABOK® Guide (Chapter 5.1 - Prioritize Requirements)states that…
Question
A business analyst (BA) is developing requirements for a project with a limited budget. The business owner will be prioritizing requirements so that low-value requirements can be de-scoped and the project remains within budget. Which of the following should the BA take into account to facilitate prioritization and ensure business objectives are met?
Options
- ADependencies
- BData flow
- CFunctional decomposition
- DTraceability
How the community answered
(35 responses)- A83% (29)
- B3% (1)
- C9% (3)
- D6% (2)
Explanation
Dependencies between requirements impact prioritization decisions, as some requirements may be critical to enabling others. If dependent requirements are removed, they mayaffect overall system functionality. BABOK® Guide (Chapter 5.1 - Prioritize Requirements)states that prioritization must considerdependencies, risks, and business value. Data flow (Option B)is useful for system modeling but does not help prioritize requirements. Functional decomposition (Option C)breaks down processes but does not prioritize them. Traceability (Option D)helps manage relationships but does not define priority directly.
Topics
Community Discussion
No community discussion yet for this question.