CCBA · Question #465
A business analyst (BA) is given an additional requirement near the end of the development phase that needs to be incorporated into the system as part of the same release. In this situation, the…
The correct answer is C. determine whether the additional requirement is traceable to a need. The first activity that the BA should perform to understand the effect of the proposed change is to determine whether the additional requirement is traceable to a need. This will help to assess the value and relevance of the requirement, and whether it aligns with the project…
Question
A business analyst (BA) is given an additional requirement near the end of the development phase that needs to be incorporated into the system as part of the same release. In this situation, the first activity the BA performs to understand the effect of the proposed change is to:
Options
- Adetermine whether stakeholders are available for further elicitation.
- Bconsult with the technical team for technical feasibility.
- Cdetermine whether the additional requirement is traceable to a need.
- Dcheck with the project manager for timeline and budget metrics.
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C71% (22)
- D19% (6)
Explanation
The first activity that the BA should perform to understand the effect of the proposed change is to determine whether the additional requirement is traceable to a need. This will help to assess the value and relevance of the requirement, and whether it aligns with the project scope and objectives. Determining stakeholder availability, consulting with the technical team, and checking with the project manager are possible subsequent activities, but not the first one.