A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and…

The correct answer is D. Item backing methods. Item tracking methods are techniques to monitor and control the status of items such as issues, defects, changes, or action items. They help to manage and resolve the outstanding issues that have been logged in an issues register. Requirements documentation, requirements…

Requirements Life Cycle Management

Question

A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and resolve the outstanding issues?

Options

  • ARequirements documentation
  • BRequirements analysis
  • CMetrics and KPIs
  • DItem backing methods

How the community answered

(52 responses)
  • A
    4% (2)
  • B
    8% (4)
  • C
    2% (1)
  • D
    87% (45)

Explanation

Item tracking methods are techniques to monitor and control the status of items such as issues, defects, changes, or action items. They help to manage and resolve the outstanding issues that have been logged in an issues register. Requirements documentation, requirements analysis, and metrics and KPIs are not techniques for managing and resolving issues.

Topics

#item tracking methods#issues register#requirements verification#defect management