A government agency has initialed a project to implement a customer registry that will be shared across multiple agencies. Early estimates indicate there will be hundreds of requirements. While…

The correct answer is B. Cost of tracing. The cost of tracing is the factor that takes precedence while determining the requirements traceability approach. Requirements traceability is the ability to track a requirement from its origin to its realization in a solution1. Requirements traceability helps to ensure that…

Business Analysis Planning and Monitoring

Question

A government agency has initialed a project to implement a customer registry that will be shared across multiple agencies. Early estimates indicate there will be hundreds of requirements. While determining the requirements traceability approach, what factor takes precedence?

Options

  • ANumber of defects
  • BCost of tracing
  • CNumber of stakeholders
  • DCost of testing

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    71% (20)
  • C
    7% (2)
  • D
    18% (5)

Explanation

The cost of tracing is the factor that takes precedence while determining the requirements traceability approach. Requirements traceability is the ability to track a requirement from its origin to its realization in a solution1. Requirements traceability helps to ensure that the requirements are aligned with the business need, the solution scope, and the test cases. However, requirements traceability also involves effort and resources to establish and maintain the links between requirements and other artifacts. Therefore, the cost of tracing should be balanced with the benefits of traceability, and the level of traceability should be appropriate for the project context and complexity2. The otherfactors, such as number of defects, number of stakeholders, and cost of testing, are not directly related to the requirements traceability approach, although they may influence the decision on how much traceability is needed.

Topics

#requirements traceability#traceability planning#cost-benefit#large-scale requirements