CCBA · Question #277
Mark is the business analyst for his organization. He is working with the solution development team and he believes that the team does not want to implement a certain portion of the requirements. The
The correct answer is B. Change the prioritization of the requirements based on overstated complexity of the project work.. In a situation where a solution development team is expressing difficulty in implementing certain requirements, it is important for the business analyst to investigate the reasons behind the team's concerns. The BA should evaluate whether the complexity is genuinely overstated or
Question
Mark is the business analyst for his organization. He is working with the solution development team and he believes that the team does not want to implement a certain portion of the requirements. The team is expressing the difficulty of the requirements and how it will be extremely challenging to complete. When Mark asks about a similar project that the team completed, they insist that this is a different type of requirements though Mark believes that it is not. What is the solution development team appearing to do to the requirements?
Options
- AGet the requirements removed from the project scope.
- BChange the prioritization of the requirements based on overstated complexity of the project work.
- CChange the prioritization of the requirements based on the past project.
- DHave the business analyst report the difficulty of the project work to the project customer.
How the community answered
(31 responses)- A3% (1)
- B74% (23)
- C6% (2)
- D16% (5)
Explanation
In a situation where a solution development team is expressing difficulty in implementing certain requirements, it is important for the business analyst to investigate the reasons behind the team's concerns. The BA should evaluate whether the complexity is genuinely overstated or if there are legitimate challenges. The BA should also consider the team's past experiences with similar projects and determine if there are any lessons learned that can be applied. Effective communication and collaboration between the BA and the development team are crucial to address these concerns and find a feasible solution.
Topics
Community Discussion