CCBA · Question #278
CCBA Question #278: Real Exam Question with Answer & Explanation
The correct answer is D. WBS. A work breakdown structure (WBS) is a tool that decomposes the project scope into smaller, manageable components. A WBS is useful for identifying activities in the business analysis approach, as it helps to define the tasks, dependencies, and resources required for each deliverab
Question
Options
- AProject management input
- BBABOK
- CA list of deliverables
- DWBS
Explanation
A work breakdown structure (WBS) is a tool that decomposes the project scope into smaller, manageable components. A WBS is useful for identifying activities in the business analysis approach, as it helps to define the tasks, dependencies, and resources required for each deliverable. A WBS also helps to estimate the effort, duration, and cost of the business analysis work, as well as to monitor and control the progress and quality of the deliverables. A WBS is different from project management input, which is an input to the business analysis approach, not a tool for identifying activities; BABOK, which is a guide that provides the best practices and standards for business analysis, not a tool for identifying activities; and a list of deliverables, which is an output of the business analysis approach, not a tool for identifying activities.
Community Discussion
No community discussion yet for this question.