CCBA Question #276: Real Exam Question with Answer & Explanation

The correct answer is B. Plan-driven approaches typically call for a significant amount of formality and detail.. A plan-driven approach to business analysis planning and monitoring is a method that defines and documents the business analysis activities and deliverables in advance, and follows a predefined process for executing and controlling them. A plan-driven approach is suitable for pro

Question

You are the business analyst for your organization. Your current project is using a plan-driven approach for the requirements, business analysis, and monitoring. Which one of the following statements best describes the plan-driven approach to business analysis planning and monitoring?

Options

  • APlan-driven approaches encourage changes that prevent errors and omissions.
  • BPlan-driven approaches typically call for a significant amount of formality and detail.
  • CPlan-driven approaches determine how priorities will be diagnosed for the project solution.
  • DPlan-driven approaches typically have meetings daily to discuss the business analysis

Explanation

A plan-driven approach to business analysis planning and monitoring is a method that defines and documents the business analysis activities and deliverables in advance, and follows a predefined process for executing and controlling them. A plan-driven approach is suitable for projects that have a clear and stable scope, low uncertainty, and high predictability. A plan-driven approach typically requires a significant amount of formality and detail, such as formal approval of requirements, detailed documentation of business analysis artifacts, and rigorous change management procedures.