CBAP Question #54: Real Exam Question with Answer & Explanation

The correct answer is A. Requirements documentation. Work products are informal, intermediate artifacts produced during analysis activities, while requirements documentation is a formal, official deliverable.

Question

Henry is the business analyst for the UUH Organization. Currently Henry is working on several work products as part of the requirements development process. He may need to share these work products with the stakeholders. Which of the following is not an example of a work product?

Options

  • ARequirements documentation
  • BInterview questions and notes
  • CMeeting agendas and minutes
  • DPresentation slides

Explanation

Work products are informal, intermediate artifacts produced during analysis activities, while requirements documentation is a formal, official deliverable.

Common mistakes.

  • B. Interview questions and notes are informal artifacts created during elicitation activities, making them valid work products.
  • C. Meeting agendas and minutes are informal records produced during analysis work sessions and are considered work products.
  • D. Presentation slides are informal materials prepared to support communication activities and qualify as work products.

Concept tested. Distinction between work products and formal deliverables