CBAP · Question #55
When is stakeholder analysis performed?
The correct answer is C. As soon as a business need is identified. Stakeholder analysis begins at the earliest possible point in the initiative - when a business need is first identified - so stakeholders can be engaged throughout the entire process.
Question
When is stakeholder analysis performed?
Options
- AAs soon as the project charter is created.
- BAs soon as the project sponsor is named.
- CAs soon as a business need is identified.
- DAs soon as a business solution is identified.
How the community answered
(37 responses)- A3% (1)
- B14% (5)
- C76% (28)
- D8% (3)
Why each option
Stakeholder analysis begins at the earliest possible point in the initiative - when a business need is first identified - so stakeholders can be engaged throughout the entire process.
The project charter is created after initial planning begins, which is too late to start identifying stakeholders who should have been engaged earlier.
The project sponsor is typically named during project initiation, which occurs after the business need has already been identified and initial analysis has started.
Stakeholder analysis should be initiated as soon as a business need is identified because stakeholders influence and are impacted by the initiative from its inception. Beginning early ensures no relevant parties are overlooked and that their needs and concerns shape the analysis from the start, before any solution direction is established.
Waiting until a solution is identified to perform stakeholder analysis is far too late, as key stakeholders should inform solution development, not react to it.
Concept tested: Timing of stakeholder analysis in business analysis