CBAP · Question #402

The business analyst (BA) is not having great success scheduling stakeholder meetings. Stakeholders say they are too busy or there are higher priority meetings on their calendars. The BA is concerned,

The correct answer is B. approval process.. Stakeholder availability and willingness to engage directly affects the approval process because requirements and deliverables must be formally reviewed and signed off by stakeholders.

Elicitation and Collaboration

Question

The business analyst (BA) is not having great success scheduling stakeholder meetings. Stakeholders say they are too busy or there are higher priority meetings on their calendars. The BA is concerned, knowing that stakeholder availability, attitude, and willingness to engage will impact the timeliness of project delivery as well as the.

Options

  • Atest execution.
  • Bapproval process.
  • Crequirements reuse.
  • Drisk analysis process.

How the community answered

(47 responses)
  • A
    19% (9)
  • B
    70% (33)
  • C
    4% (2)
  • D
    6% (3)

Why each option

Stakeholder availability and willingness to engage directly affects the approval process because requirements and deliverables must be formally reviewed and signed off by stakeholders.

Atest execution.

Test execution is driven primarily by the test team and depends on system readiness and test case completion, not on stakeholder meeting availability.

Bapproval process.Correct

The approval process is wholly dependent on stakeholder participation, as stakeholders must review, provide feedback on, and formally sign off on requirements and project deliverables. When stakeholders are unavailable or disengaged, approvals stall, creating a bottleneck that compounds delivery delays beyond simple scheduling issues.

Crequirements reuse.

Requirements reuse is a future-oriented activity tied to documentation quality and repository management, not a primary outcome impacted by current stakeholder engagement.

Drisk analysis process.

Risk analysis is one collaborative activity stakeholders contribute to, but it is not the ongoing process most directly bottlenecked by sustained stakeholder unavailability throughout the project.

Concept tested: Stakeholder engagement impact on approval process

Topics

#stakeholder engagement#stakeholder availability#meeting facilitation#approval process

Community Discussion

No community discussion yet for this question.