nerdexam
Microsoft

74-343 · Question #98

74-343 Question #98: Real Exam Question with Answer & Explanation

Sign in or unlock 74-343 to reveal the answer and full explanation for question #98. The question stem and answer options stay visible for context.

Question

You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project. The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20. You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time. What should you do?

Options

  • ACreate a material resource with a material label of gallons.
  • BCreate a cost resource, add the resource to a task, and enter $25 in the actual cost.
  • CCreate a material resource with a material label of gallons.
  • DCreate a cost resource, add the resource to a task, and enter $2520 in the actual cost.

Unlock 74-343 to see the answer

You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-343 Practice