nerdexam
Microsoft

74-343 · Question #98

You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter…

The correct answer is B. Create a cost resource, add the resource to a task, and enter $25 in the actual cost. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project. The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20. You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time. What should you do?

Options

  • ACreate a material resource with a material label of gallons.
  • BCreate a cost resource, add the resource to a task, and enter $25 in the actual cost.
  • CCreate a material resource with a material label of gallons.
  • DCreate a cost resource, add the resource to a task, and enter $2520 in the actual cost.

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    74% (20)
  • C
    4% (1)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice