74-343 · Question #98
You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter…
The correct answer is B. Create a cost resource, add the resource to a task, and enter $25 in the actual cost. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Professional 2013. You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project. The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20. You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time. What should you do?
Options
- ACreate a material resource with a material label of gallons.
- BCreate a cost resource, add the resource to a task, and enter $25 in the actual cost.
- CCreate a material resource with a material label of gallons.
- DCreate a cost resource, add the resource to a task, and enter $2520 in the actual cost.
How the community answered
(27 responses)- A15% (4)
- B74% (20)
- C4% (1)
- D7% (2)